Project Overview Map (above)

Development is planned for several areas within Clearwater County. While the project aims to improve connectivity across all five funded areas, each area consists of multiple sub-areas where construction will occur. Please note that fiber installation is confirmed only for the sub-areas listed in the tables below. The broader areas will be considered as demand grows and resources allow.

Project Funding

Funding Image

This project is funded through the Universal Broadband Fund, a Canadian federal initiative with additional support from the Alberta provincial government. The funding aims to bring reliable, high-speed internet to rural and underserved areas within the county. We are grateful for this support, which is instrumental in improving connectivity for residents. For more information on the grants, please visit the official UBF project page here.

Construction Progress by Area

UBF-03250: Martins Trailer Court, Ferrier Acres, Ullin, and Crimson Lake Area
Area Name Current Status Construction Start Date Estimated In-Service Date Notes
11A_LOUIS_LAKE_CONNECTOR Construction Planned TBD TBD -
403041_RR8-5_EXT Construction Planned TBD TBD -
CRIMSON_NORTH Construction Planned TBD TBD -
CRIMSON_SOUTH Construction Planned TBD TBD -
CRIMSON_WEST Construction Planned TBD TBD -
FERRIER Construction Planned TBD TBD -
FERRIER_ACRES_EAST Construction Planned TBD TBD -
FERRIER_ACRES_NORTH Construction Planned TBD TBD -
FERRIER_ACRES_WEST Construction Planned TBD TBD -
TWIN_LAKES_CAMP_EXT Construction Planned TBD TBD -
UBF-07119: Chedderville, Burnstick Lake, Butte, Caroline and Crammond Area
Area Name Current Status Construction Start Date Estimated In-Service Date Notes
BeaverLakeCamp_RR70 Construction Planned TBD TBD -
CaronlineGas_RR61_FretWorks Construction Planned TBD TBD -
Chedderville_TWP372_RR64 Construction Planned TBD TBD -
ClearwaterCollege_Ricinus_HWY591 Construction Planned TBD TBD -
ClearwaterTCE_TWP360 Construction Planned TBD TBD -
ClearwaterTrading_HWY591_RR65 Construction Planned TBD TBD -
Congresbury_RR74A Construction Planned TBD TBD -
Crammond-E_TWP354_RR53-52 Construction Planned TBD TBD -
Crammond-W_TWP354_RR55-60-61 Construction Planned TBD TBD -
DovercourtHall-W_TWP372 Construction Planned TBD TBD -
HWY752_CowLake_RR384 Construction Planned TBD TBD -
HWY752_RR80_HiddenValleyCl Construction Planned TBD TBD -
HWY752_WestRvATVPark Construction Planned TBD TBD -
JamesRiverBridge-E_HWY587_RR52-50_TWP350 Construction Planned TBD TBD -
KlassenOildField_TWP374_CowboyTrl Construction Planned TBD TBD -
LazyMLodge_TWP372_RR53 Construction Planned TBD TBD -
MacintoshIndustries-S_RR63_TWP365A Construction Planned TBD TBD -
ParadisLogging_CowboyTrl_TWP365A Construction Planned TBD TBD -
RR63_BeaverRunTrl Construction Planned TBD TBD -
RR64_TWP360 Construction Planned TBD TBD -
RR90 Construction Planned TBD TBD -
Southfork Rd Construction Planned TBD TBD -
StarkRanchResort_JamesRiverRd Construction Planned TBD TBD -
Strachan-E_TWP380 Construction Planned TBD TBD -
Strachan-NW_RR92A Construction Planned TBD TBD -
StrachanGasPlant Construction Planned TBD TBD -
StrubelLake_RR75&80 Construction Planned TBD TBD -
TWP352-351C Construction Planned TBD TBD -
TWP384A&385_RR84 Construction Planned TBD TBD -
WhitecapGasPlant_RR74-75 Construction Planned TBD TBD -
UBF-07121: Codner Area
Area Name Current Status Construction Start Date Estimated In-Service Date Notes
CanyonCreekGolf_Hwy12_RR61-62-63_TWP410 Construction Planned TBD TBD -
Hwy12_RR70 Construction Planned TBD TBD -
Hwy22_GrapevineHouse_FriscoCommunityHall Construction Planned TBD TBD -
Hwy22_TWP412-413-414_RR74 Construction Planned TBD TBD -
Hwy53_RR62-63 Construction Planned TBD TBD -
Hwy53_RR64A-65_Hwy22 Construction Planned TBD TBD -
Hwy598_RR65 Construction Planned TBD TBD -
Hwy761_AuroraHall_TWP415A_RR50 Construction Planned TBD TBD -
Hwy761_TWP423_Hwy53_OpenCreekDam Construction Planned TBD TBD -
RR60-55_TWP415A_Hwy761 Construction Planned TBD TBD -
RR63 Construction Planned TBD TBD -
RR63_LangbergHomes_TWP412-414_RR62 Construction Planned TBD TBD -
RR63_TWP420-422_OrasRd Construction Planned TBD TBD -
RR64A Construction Planned TBD TBD -
TWP400_CowboyTr_ParadiseTr Construction Planned TBD TBD -
TWP402_RR70 Construction Planned TBD TBD -
UBF-07122: Carlos Area
Area Name Current Status Construction Start Date Estimated In-Service Date Notes
Hwy598_RR63_Codner Construction Planned TBD TBD -
Hwy598_RR64A_RR65 Construction Planned TBD TBD -
Hwy761_RR51-52-53_Hwy12 Construction Planned TBD TBD -
RR43-45_TWP413_GimletCommunityCentre Construction Planned TBD TBD -
RR54-55_TWP410-413 Construction Planned TBD TBD -
RR60_TWP410-413 Construction Planned TBD TBD -
RR62-61A-61_TWP402_BeaverFlatsRd Construction Planned TBD TBD -
RR65-64-63_TWP401A Construction Planned TBD TBD -
RR71_BigRockWasteDisposal Construction Planned TBD TBD -
TWP394A-402_RR45-50_MoesBoardingKennel Construction Planned TBD TBD -
TWP395_NorthlandDr_RR65_TWP400 Construction Planned TBD TBD -
TWP410-412-413_Hwy761_WagnersLivestock Construction Planned TBD TBD -
TWP410-413_RR50 Construction Planned TBD TBD -
UBF-07123: Nordegg, Saunders and Horburg Area
Area Name Current Status Construction Start Date Estimated In-Service Date Notes
150082+151058_HWY11_DROPS Construction Planned TBD TBD -
404084B_HWY734_EXT Construction Planned TBD TBD -
CAMP_ALEXO_DROP Construction Planned TBD TBD -
CHAMBERS_CREEK Construction Planned TBD TBD -
HORBURG_EAST Construction Planned TBD TBD -
HORBURG_WEST Construction Planned TBD TBD -
MISTY_VALLEY_ESTATES Construction Planned TBD TBD -
NORDEGG_CENTRAL Construction Planned TBD TBD -
NORDEGG_INDUSTRIAL Construction Planned TBD TBD -
NORDEGG_NORTH_SUBDIVISION Construction Planned TBD TBD -
NORDEGG_OUTER Construction Planned TBD TBD -
SHUNDA_CAMP_EXT Construction Planned TBD TBD -
SUNCHILD_R_SOUTHROAD Construction Planned TBD TBD -